The essentials in 3 points

  • Air-to-water heat pump: CHF 5,000 for a single-family home (measure M-05).
  • Geothermal or water-to-water heat pump: CHF 20,000 for a single-family home (measure M-06).
  • The application must be approved before any order or delivery of equipment, otherwise the grant is lost.

2026 scale

The official amounts, measure by measure.

Connection to an anergy network: M-05 and M-06 amounts reduced by 50%. The subsidised output is capped at 50 W per m² of energy reference area before the work.

Worked example

A 10 kW house, calculated on the scale.

Fictitious example: a single-family home heated with oil, whose thermal study sets the need at 10 kW.

With an air-to-water heat pump (M-05)
CHF 5,000
With a geothermal heat pump (M-06)
CHF 20,000
Difference in favour of geothermal
CHF 15,000

Any municipal grants and the tax deduction come on top of these amounts. Geothermal costs more to buy: see the prices on our geothermal page before comparing.

Conditions

The conditions to meet before filing.

Replacing fossil or electric heating

The heat pump replaces main heating running on oil, natural gas or fixed electric resistance. New buildings are not eligible.

100% renewable heating and hot water

After the work, heating and domestic hot water must be fully covered by renewable energy, including hot water during the heating season.

A CECB® for buildings from before 2000

The envelope must be rated A to E, or A to C above 1,000 m altitude for an air-to-water heat pump. The CECB® is updated after the work.

A certified installation

Up to 15 kW, the heat pump is installed to the heat pump system module standard. Above that, a SwissEnergy performance guarantee and a quality label. For geothermal, the driller must hold the GSP label.

Procedure

The application, step by step.

  1. 01

    Thermal study and quote

    Output calculation, choice of technology and, for a building from before 2000, a CECB® drawn up or updated.

  2. 02

    Filing on the Building Programme portal

    Form signed by the owner, detailed quote, system module certificate or performance guarantee, CECB®, and for geothermal the quote of the GSP-labelled driller.

  3. 03

    Grant decision

    The cantonal energy directorate reviews the file. Nothing is ordered or delivered before its written decision.

  4. 04

    Work

    Order and installation once the grant is approved. If your municipality pays a grant, its application is filed in parallel.

  5. 05

    Completion notice and payment

    Completion notice on the same portal, with paid invoices, the commissioning report and the updated CECB®. The canton then pays the grant.

Frequently asked questions

Your questions on grants in Vaud.

How much is the Vaud grant for a heat pump in 2026?

+

CHF 5,000 for an air-to-water heat pump in a single-family home (M-05), CHF 20,000 for a geothermal or water-to-water heat pump in a single-family home (M-06). For other buildings, M-05 pays CHF 400 per kW above 15 kW and M-06 pays CHF 4,000 + CHF 800 per kW above 20 kW.

Must the application be filed before the work?

+

Yes. The application must be approved before any order, delivery or start of work. Equipment delivered on site before the grant decision disqualifies the application.

Is a new building eligible?

+

No. M-05 and M-06 fund the replacement of oil, natural gas or fixed electric resistance heating in an existing building.

My building dates from before 2000: what else is required?

+

A CECB® with an envelope rated A to E, or A to C above 1,000 m altitude for an air-to-water heat pump. If the envelope is rated F or G, insulation is needed before the application can be filed.

Can the cantonal grant be combined with a municipal grant?

+

Yes. Several Vaud municipalities pay their own grants, with amounts and budgets that change from one year to the next. Check with your municipality's energy department before signing.

Is the remaining cost tax-deductible?

+

Yes, the net investment after grants is deductible from taxable income as an energy-saving investment. Your accountant can tell you which tax year to attach it to.

Source: Building Programme 2026 conditions of the State of Vaud (version 1.1 of 12.01.2026), M-05 and M-06 fact sheets. For the application details, pitfalls and municipal grants, read our guide heat pump grants in Vaud 2026. For geothermal, see also our page geothermal heat pump.

Swiss landscape at sunset

Free quote

Free energy studyfor your home,no obligation.

On-site visit, consumption analysis, detailed cost simulation. Full quote delivered within seven days. If your project is not technically or financially viable, we tell you straight.

  • 7 daysDetailed quote turnaround
  • FreeOn-site study, no commitment
  • 100 %Subsidy applications handled for you
Prefer to talk? 0800 800 840

Study request

We will call you back within 48 hours.

By submitting this form, you agree to be contacted by our team. No data is shared with third parties. See our privacy policy.